Let's talk Dependencies. A Dependency is a relationship between two activities, and is most often encountered in the Project Schedule. In this case they are used to structure the order of tasks, to help you plan the Project. Logically, there are four type of Dependency relationship - shown in the diagram below:
Lag and Lead time in also a concept in these logical relationship. Lag represents a time delay following task 1 before task 2 initiates, such as waiting for paint to try before fitting the wall lights. Lead is essentially negative lag, for example you could start fitting wall lights on one wall before all of the other walls paint has dried.
We've seen people make the mistake of thinking that by logging Dependencies in the logic of the schedule, that's them covered. But the problem with this is that a big schedule may have thousands of tasks and thousands of dependencies - how do you "see the wood for the trees"? You tend to find that, although there are many Dependencies on a Project, there are only a few key Dependencies. It's not worth making a special effort to track pretty mundane day-to-day dependencies which we take for granted, but these key Dependencies are critical to your Project's success - and so warrant special attention. You can think of these key Dependencies in terms of a "Give-Get" relationship; either you are Giving or you are Getting. Typically it will be a key delivery from a 3rd party or supplier, or a key milestone date you have to deliver something to the client. In this case you should use a Dependencies Log to track them; this will make sure you maintain visibility of them and are able to more easily monitor them. An alternative is to recognise Dependencies as a source of Risk on your Project, which they certainly are; any "Gets" which you are waiting for from outside of the Project are not under your direct control. So you may chose to scan Dependencies to identify Risks that you need to log and manage, or you may actually integrate your Dependency Management into your Risk Management Tool/Process entirely. What experiences do you manage Dependencies on your Project? And if you need a Project Dependency Log Template we have you covered in our template store! Stay Healthy! Project Health Check - projecthealthcheck.org
0 Comments
Leave a Reply. |
Mission:To understand why do Projects Fail and what we need to do differently to stop it happening again. Archives
March 2018
Categories
All
|